How does a data center get connected to the US power grid?

Explainers
A high-voltage transformer with dark ceramic bushings stands inside a fenced switching yard.
Editorial illustration of a transformer in an electrical switching yard.
A data center grid connection starts with a request for power. It ends when the utility can supply the site. Deals and permits can show real progress along the way. The trick is to read each record for the step it confirms.

Start with the utility and the load

Find the power company for the site. It may sell power or own the wires. A second firm may own the high-voltage lines. The site may need power for one building first. Ask how much it wants for each phase and when.
A large load request gives the site, the power it needs and the dates it wants. A grid study can show which lines or substations need work. It can also show how much power the site could get before that work is done. Local rules set the order of these steps.
A load request asks to take power from the grid. A generator seeks rights to supply it. Each can call for a study. The Federal Energy Regulatory Commission’s large-load proceedings show why rules for these sites can vary by grid region. A listing in a generator queue leaves questions about power service to the data center open.

What signed terms can tell you

A service deal can set dates and costs. Check which phase it covers and where power will reach the site. The first block of power may need a new line, a transformer or a test of the site gear. Those steps can move the date.
In Virginia, Dominion asked regulators to review its process for delivery-point requests that power distributors make to serve data centers. The State Corporation Commission’s order on Dominion’s queue case records that filing as a separate matter from earlier approvals to build lines. Search an official docket by the utility’s legal name as well as the data center’s project name.

Read the Apollo–Twin Creeks docket in order

March 27, 2024 | Utility application. Dominion filed for a new transmission line and five substations in Loudoun County. The Virginia commission’s final order in case PUR-2024-00044 says the utility sought facilities to serve three data center customers. Testimony in a later Virginia rate case put their combined load at 1,372 MW.
February 5, 2025 | State approval. The commission gave Dominion authority to build. The order says the work must be built and in service by September 30, 2028. It also sets a September 30, 2029 sunset for the certificate if the project has not been energized. Dominion can ask for more time.
Customer service | Dates still open. The order gives no date or MW figure for the first phase. It gives no meter reading for either site. Look for a later notice from the utility that confirms power is live.

Check which part of the project is live

A utility can energize the new line before servers take power at full load. Ask for the site, the date service began and how much the utility can serve at that stage. These records help explain the difference between a project moving through the grid process and the compute infrastructure a customer can put to work.
A grid milestone answers a different question from a power purchase. Our guide to reading power deals shows how to separate a compute commitment from an agreement to deliver electricity.