CleanSpark is talking to more potential tenants for two Texas AI data center sites after a period of exclusive talks expired. Its Georgia data center customer is still in the mix. The company also says it has received state permits for one of the Texas sites.
CleanSpark gave the update on November 24 in its earnings release filed with the SEC. The company says the exclusive period for Sealy and Brazoria ended while the rules were in flux. It gave no date for a lease at either site. It said the Texas Commission on Environmental Quality had issued permits for Brazoria.

What Texas has cleared so far

CleanSpark lists 285 megawatts at Sealy and 300 megawatts for the first phase in Brazoria. Texas grid operator ERCOT put that 585 MW in its conditional baseload group. The company first disclosed the status in a September update. A second phase in Brazoria could add up to 300 MW. That phase falls under a separate group that needs further study.
ERCOT calls the first round of large power users under its new rules Batch Zero. It looks at these projects as a group to see how much demand the grid can handle and where it needs stronger power lines. The state approved the rules in June. The group study covers sites that need at least 75 MW and meet the entry terms.
ERCOT says the first classifications are provisional. A site may still have to pass checks or turn in more data before it can connect. The state permits for Brazoria cover a separate part of the build.
The Texas power figures describe the scale of the sites. They measure a different thing from power that a host has set aside for servers. In the OpenAI deal with TensorWave, for example, 457 MW refers to the power for the computing gear. Cooling and other site equipment draw power as well.

In Georgia, a tenant and a date

CleanSpark says it remains on track to hand over its first data hall in Sandersville, Georgia, in November 2027. It signed a 20-year lease with a global technology company in July. Its annual report puts the rent at about $6.56 billion over the first term. The lease covers 175 MW of power for computer equipment. CleanSpark says it has the main building permits and raised about $2.28 billion in debt for the work.
The annual report also shows how early this shift is. CleanSpark's data center unit booked no sales in the year through September. It expects work to fit out the halls for its tenant to bring in revenue before the lease starts. The company's $576.5 million in sales for the year came from Bitcoin mining. That was down 25% from the prior year.

What comes next for the Texas sites

A signed tenant would give Sealy or Brazoria a source of rent. A final grid decision would help show how much power the sites can draw and when. CleanSpark's update leaves both dates open. Sandersville offers the company's nearest test of what happens after it signs a lease and funds a build. Its first hall still has about a year to go.